Twenty-one case studies across wind, solar, storage, and transmission, showing how we find the risks others miss and get deals to closing.
100 entities needed subordination and crossing agreements before this 199 MW Oklahoma wind project could reach debt and equity financing. All of them were resolved.
An owner’s affidavit saved tens of thousands in survey costs and kept refinancing on schedule for a 44 MW project in Riverside County.
Minerals insurance secured for a gas-fired plant, working through complex mineral rights across multiple jurisdictions so financing could close.
Complex closing support on Laurel Mountain Wind, coordinating every party through to a successful financing close.
A year-end deadline, a holiday calendar, and every financing requirement still to meet. The project qualified.
Legal access secured through negotiation between private landowners and tribal groups, clearing the way for development.
A 20 MW solar project with an internal EPC contractor still needed mechanics lien coverage to satisfy the lender at closing.
Prescriptive rights issues on the Mount Signal SDG&E project resolved so title insurance and financing could move forward.
Subsurface rights untangled and minerals insurance secured alongside ALTA coverage, meeting every lender requirement.
Critical project documents recorded on time despite a local recorder’s office that wasn’t making it easy.
EPC bonding requirements resolved so the lender’s required title insurance endorsements could be issued.
A complete, organized handoff from development to commercial operations, protecting compliance for the life of the project.
Lender endorsement requirements met by proving contiguity, either physically or through documented legal access rights.
Access ambiguity resolved and direct legal access confirmed, so title insurance could be issued before financing.
Legal descriptions reconciled across every parcel, catching discrepancies long before they could delay the close.
Every legal interest in the project verified and confirmed, which is what financing readiness actually requires.
A 44 MW repower meant updating all site control and title documentation. Two hundred documents, re-papered.
Community solar projects energized once every interconnection document and right was in place.
A new survey and filed parcel map established clear title insurance coverage for a 6 MW project footprint.
Legacy third-party rights on a 150 MW Imperial County solar project were blocking title insurance. They were terminated.
Lease recording errors created a mismatch with county records and stalled the project. We resolved it and got it moving.
No case studies match that filter.