Power Output
44 MW
Documents
200+
Service
Re-Power / Title
Technology
Wind
Watch Kimberlee explain this case
When a wind project is repowered โ replacing aging turbines with newer, larger ones โ it's not just a construction project. It's a legal and title event. Every lease, easement, license, and site control document that references the old turbines, their locations, or their specifications may need to be updated or replaced to reflect the new project configuration.
For this 44 MW wind re-power project, TerraPro Solutions faced the task of re-papering over 200 documents โ a massive administrative and legal undertaking that had to be completed before the repowered project could be financed.
TerraPro Solutions built a complete document inventory, cataloged every instrument that required updating, and systematically worked through each one โ identifying what changes were needed, preparing amended or restated documents, and coordinating execution with each counterparty.
With 200+ documents and multiple counterparties, project management was as important as legal analysis. We tracked every document through drafting, negotiation, execution, and recording โ ensuring nothing fell through the cracks on the path to financing readiness.
All 200+ documents were re-papered, executed, and recorded. The repowered project was finance-ready with a clean and updated document set โ enabling the financing to close and the new turbines to be installed.
200+ documents re-papered. Complete site control and title document update completed for 44 MW wind re-power โ project financing-ready with clean updated documentation.
Project details
Have a similar challenge?
Our team has worked on hundreds of projects across every stage. Let's talk about yours.
Talk to our teamTerraPro Solutions uses Accessibility Checker to monitor our website's accessibility.