North American Clean Energy Issue
May/june 2021
Wind farm repowering encompasses anything from completely decommissioning aging wind turbines and replacing them with newer (larger, more efficient turbines) at the same site, to partial repowering by replacing key components in existing wind turbines to improve generating capacity and reliability. Repowering may also modernize interconnection infrastructure, including designing new roads or adding more turbines. The goal is to have a wind farm with a greater and more efficient generating capacity than before.
Follow us on social
While repowering can help avoid the prospect of scouring an ever-shrinking inventory ofย Critical aspects to examine before moving forward include the following:
ย
โข Regional and local laws and jurisdictions: Projects that were developed in the late 80โs and early 90โs may be subject to changes in laws and regulations affecting local and regional jurisdictions. In the past, a developer may have had to consult with various agencies at the federal, county or city level for permitting. A thorough review of current regulations in local and regional jurisdictions is critical to ensure that repowering plans comply with prevailing laws, and to understand any costs or delays that could result from legal changes, particularly if a developer wants to take advantage of tax credits.
ย
โข Structure of real property agreements: A comprehensive review of the original site control documents will identify whether limiting factors or real property tax and assessment implications could affect repowering. For tax purposes, many local tax authorities consider the initial term of the lease from its inception; something that cannot easily be altered with the extension of a lease to accommodate the repower of the project for financing.
โข New wind-turbine technology: Turbine technology has dramaticallyย improved within the last ten years. Average capacity factor and efficiency hasย increased while costs have decreased, providing key incentives for developers
in monetizing repowered projects.
ย
โข Integration of hybrid technologies: As projects are re-engineered, the option ofย adding batteries and/or solar will be of interest to many developers. One of theย obvious benefits of co-locating wind, solar and/or storage is the ability to maximizeย existing grid infrastructure. Storage is likely to become a key consideration forย developers seeking to maximize revenues when repowering wind farms.
ย
โข Financing: There has been a dramatic shift in the financing environment forย wind projects, including title insurance pertaining to a severance of the mineralย and surface estate. In the past, developers did not have to be concerned with aย severance of the minerals evidenced in title reports for purposes of obtainingย ALTA coverage, because it was believed that the spacing of the wind turbinesย across the property allowed for other uses. The risk environment has significantlyย changed, so that wind projects now face constraints in addressing the rightsย of third-party mineral holders. Title must be carefully examined to identifyย potential rights of other parties to exploit the project property for oil, gas, and coalย development. Accommodation agreements or other affirmative documentationย may be required to control the rights of these parties to access the property.
ย
Checklist for wind repowering:
ย
1. Identify local and regional zoning and permitting requirements includingย restrictions on property, public right-of-way, as well as visual and safety setbacks.
2. Assess new turbine technology, determine which technology will conformย to the proposed site.
3. Model the feasibility and suitability of combining technologies.
4. Model the legacy operating wind data.
5. Confer with the Department of Defense.
6. Submit wind turbine coordinates to Federal Aviation Administration.
7. Undertake Phase I Environmental Site Assessment.
8. Evaluate the feasibility of operating the project through the remaining PPA term toย compare the results to repowering the current wind turbines.
9. Review real estate agreements to determine suitability for repower and economicย impact of regeneration or extension.
10. Identify potential off-takers and negotiate a new Power Purchase Agreement.
11. Perform an early and detailed review of the title work to address the potential ofย third-party mineral holders to allow for negotiation of affirmative agreements.
ย
A tremendous advantage of a wind repower project is that it is typically safe or โde-riskedโย from community and jurisdictional concerns because the wind farm already exists. Inย addition to creating a viable investment, repowering means that legacy operating and existingย wind data can mitigate many of the challenges that face developers in building on a new site.

Kimberlee Centera
Kimberlee Centera is a risk management expert for the development and financing of large-scale generator energy projects for public utilities and community development. She possesses the expertise to identify, manage and mitigate risk. Kimberlee works on complex high-value projects, such as a wind farm development that powers a JP Morgan Chase property. A leading renewable energy expert, Kimberlee has been a guest on numerous radio programs including National Public Radioโs Marketplace. She frequently serves as a speaker and educator at wind and solar conferences. Kimberlee Centera Email: [email protected]